Petch Building - Roofing and Cooling Plant Installation
As part of the Science Buildings Renewals project, cooling equipment will be installed on the Petch building roof. Work will include partial re-roofing at the west end of Petch and installation of a steel platform, two large cooling plants (chillers) and a pump house. If a more detailed schedule is required, please contact the project manager.
September 9, 2017 through November 9, 2017.
- Concrete and Steel Supports – Tuesday, September 5, 2017.
- Roofing Work – Monday, September 25, 2017
- Steel Platform – Tuesday, October 3, 2017
- Chiller Units – Thursday, October 19, 2017
- Pump House – Monday, October 30, 2017
View/ Download Facilities Management Notice - Petch Building - Roofing and Cooling Plant Installation
Contact/ Organizer name: Scott Kingham, Project Manager or David Hill, Colliers Project Manager