Parking Lot Repairs in various locations – Revised Schedule
Parking Lots: 2, 6, 7, 9, 12, 15
Facilities Management and Island Asphalt will be doing asphalt repairs and re-paving in various parking lots around campus from June to August 2023.
The proposed schedule is as follows;
- June 12th - Lot 4 - Completed
- June 13th – Lots 1 & 2 - Completed
- June 15th & 16th – Lot E - Completed
- June 19th to July 3rd – Lot 7
o Asphalt removal completed 2023-06-20
o Patch paving planned for 2023-06-30
o Top lift overlay planned for 2023-07-03
- June 21st to July 3rd – Lot 2 (N.W.)
o Asphalt removal 2023-06-21 to 23
o Patch paving planned for 2023-06-30
o Any final paving cleanup 2023-07-03
- June 28th to 30th – Lot 12
o Asphalt removal June 28th to June 29th
o Paving June 30th
o Lot ready for use Monday July 3rd
- July 4th & 5th – Lot 15
- July 6th to 10th – Lot 2 (N.E.)
- July 11th to 14th – Lot 2 (S.E.)
- July 20th to 26th – Lot 2 (S.W.)
- July 27th to Aug 4th – Lot 9
- Aug 8th to 10th – Lot 6
June 19 - August 10, 2023
View/ Download Facilities Notice - Parking Lot Repairs-REV Date
Contact/ Organizer Name - Randy Carter, Project Manager
Contact/ Organizer Email Address - rcarter@uvic.ca