ELW Safety and Energy Upgrades- Fume Hood Impacts
Engineering Lab Wing: B120, B239, B225
Cairn Mechanical and Universal Sheet Metal will be installing controls in support of the recent mechanical system upgrades in ELW’s B wing. This work will occur over the next two weekends and will require a temporary turndown of the supply air. This will in turn affect the containment ability of associated fume hoods.
During these select weekend days, we request that you temporarily close and refrain from using your fume hoods in the following labs.
B120 MiNa lab
Saturday, November 16th
Sunday, November 24th
B239 BSL2 Lab & B225 H2 Lab
Saturday, November 23rd
Sunday, November 24th
We apologize for any inconvenience.
8:00 am – 3:00 pm
View/Download Facilities Notice: ELW Safety and Energy Upgrades- Fume Hood Impacts
Contact/Organizer Name: Jen Miley, Project Manager
Contact/OrganizerEmail address: jmiley@uvic.ca