Cornett Building - Partial Roof Replacement - REVISED Update

Cornett Building – West Side of the Building

Facilities Management is working with Flynn Canada on the roof
replacement of the west half of the Cornett building starting Monday, June
24th with completion targeted for August 16th.

The areas of replacement including the contractor’s mobilization area are
shown on the attached map.

This work includes the removal of the metal flashings that have a minimal
amount of caulking that is asbestos containing. The workers removing the
flashing will be using removal procedures mandated by WorkSafe BC. This
work is scheduled to start on Monday, June 24th and be completed late in the day Friday June 28th. Please keep windows closed on these days.

There will also be noisy work starting June 24th to July 5th while the rock
ballast is being vacuumed off the roof areas. The vacuum truck will be
located in the mobilization area. Please keep windows closed during this
time as this work may create dust.

There will be a crane on site:

• June 28th to unload materials from the roof
• July 4th to load materials on the roof

Please respect the directions of safety officers and signage during
this time.

Monday, June 24 to Friday August 16, 2024

View/ Download Facilities Notice - Cornett Partial Roof Replacement - REVISED Update

Contact/ Organizer Name - Terry Moen, Project Manager

Contact/ Organizer Email Address - tmoen@uvic.ca